Translate

Translate This Page

Thursday, December 1, 2011

PJI Holdings secures RM59.64m contracts at KLIA2 (Edge)

PJI HOLDINGS BHD []’s unit has secured two contracts worth RM59.64 million at the KLIA2 involving the low voltage system for several locations at the KLIA2.

It said on Wednesday its unit P.J. Indah Sdn Bhd had accepted the letter of award from BINA PURI HOLDINGS BHD [] to formalise the sub-contract valued at RM25.16 million.

The contract included the supplying, installation and maintenance of the low voltage system for the skybridge (sector 4), contact pier (sector 5), satellite building (sector 6) and contact pier (Sector 7) of KLIA2.

In a separate statement, it said P.J. Indah had also accepted a RM34.64 million contract from UEM CONSTRUCTION [] Sdn Bhd.

It said the contract was for the design, supply and maintenance of the low voltage system, uninterruptible power supply and lightning protection system at KLIA2.

PJI said the duration of the second sub-contract was for eight months and was expected to be complete by April 1, 2012.